27J Schools • 2021 Bond Program
Southlawn Elementary
PHASE II
PROJECT STATUS
- 100%
Planning
We’re in the beginning stages of this project. While you may not see anything happening yet, this phase can involve steps such as land acquisition, the hiring of architects and contractors, the creation of design and construction documents and building a project schedule.
Breaking ground
The planning phase is complete and we’re ready to start construction. This means you’ll start to see fencing, trailers and equipment appear on the site as we prepare to begin construction.
Construction
It’s time to get to work on building this new, important investment for our students and our community.
Completion
We did it! Thanks to the support of the 27J Schools community, this project has been completed as promised. Thank you for helping us build strong schools for strong communities.
PROJECT DETAILS
- Location: 10075 Walden Street, Commerce City
- Completion Dates:
Phase 1: August 1, 2022
Phase 2: September 19, 2022
- Architect: Hord Coplan Macht
- Contractor: JHL Constructors
- Owners Representative: Anser Advisory
- Ground Breaking: September 22, 2021
Southlawn Updates
Phase I of Southlawn Elementary was completed and opened to students in August 2022. Phase II of construction was completed and opened to students in September 2022.
More Southlawn?
Our contractor partner, JHL Constructors, has a project site where they post updates and progress photos for Southlawn Elementary.